The tract, the stakes, the freeze.
By Ellis Ward | November 26, 2026
A New Jersey developer filed suit in state Supreme Court last month, arguing that East Fishkill's three-year data center moratorium is unconstitutional and amounts to a targeted attack on its project before any permit was ever filed. The case puts a local planning tool under legal pressure at the same moment 97 New York municipalities have adopted similar freezes and Governor Kathy Hochul has moved to restrict the industry at the state level.
A Lawsuit Before Any Application
Treetop Development, based in Teaneck, N.J., filed an amended complaint on October 26 in state Supreme Court in Poughkeepsie. The company argues that Local Law No. 3 of 2026 constitutes an abuse of the town's zoning authority and an unconstitutional regulatory taking. Its legal team characterizes the moratorium as a reaction to "negative social-media criticism and mounting public pressure" rather than a principled planning decision.
The East Fishkill Town Board voted 5-0 on June 25, 2026, to adopt the law. It took effect immediately and runs through July 1, 2029. The board voted unanimously. No dissent appears in the public record.
Reporting note: No case or index number has been reported publicly. The names of Treetop's attorneys have not appeared in available reporting. No hearing date has been scheduled, as far as reporting reflects. No damages figure has been stated. The town had not responded publicly to the lawsuit as of the reporting available for this article.
Treetop's Concept: 1,000 Megawatts in Dutchess County
The scale of Treetop's proposal sets it apart from most data center projects under discussion in the Hudson Valley. Reuben Twersky, the company's director of development, has been pursuing a concept internally called "1 Gig Data Center East Fishkill." A thousand megawatts would draw roughly the equivalent of Cricket Valley Energy Center's 1,100-megawatt output. Cricket Valley, a natural gas plant about 20 miles from the site, opened in 2020 and powers a substantial portion of the mid-Hudson Valley. Treetop's data center would draw a comparable load from the same regional grid.
The site is a wooded tract in East Fishkill. The company has had a presence on the parcel since 2023, when it was developing a warehouse concept. That plan originally called for one million square feet of industrial space; it was later revised to 765,000 square feet. The data center concept appears to have developed alongside those warehouse plans.
Treetop secured a spot in the New York Independent System Operator's interconnection queue. That NYISO filing is the standard step a developer takes to reserve capacity on the state grid. It was the only formal submission the company made to any authority before the moratorium passed. No application landed on the town's desk.
The proposed build-out would proceed in two phases: 500 megawatts by 2028 and the remaining 500 megawatts by 2030. A company letter cited in the lawsuit filings shows Treetop coordinating with Central Hudson Gas and Electric, Consolidated Edison, the New York Power Authority, and other utility stakeholders. That coordination happened through private channels, not through the town.
Local Law No. 3: A Planning Pause, Not a Permanent Ban
The East Fishkill board framed its June decision as a measured response to rapid industry growth, not an outright prohibition. Local Law No. 3 bars new data centers drawing more than 20 megawatts from obtaining permits in the town for three years. Facilities under 20 megawatts that are ancillary to an existing use are exempt. Projects eligible for an Economic Development Special Permit are also carved out.
The stated rationale was straightforward. The board said it needed time to wait for federal and state studies on the power consumption, water demand, noise, and heat output of large-scale data centers before it could responsibly permit them. The law also separately froze industrial development applications through December 31, 2026.
Town Supervisor Nicholas D'Alessandro and Councilmember Marianne Flores pointed to the creation of the East Fishkill Data Center Study Task Force as the constructive companion to the freeze. Flores expressed hope that the task force would deliver findings before the moratorium expired. The town's position is that it needs data before it can make sound decisions. That is the planning authority it claims the courts should respect.
"We Can't Drink Data"
The June 25 hearing was not quiet. Residents filled the meeting room before the vote and made their opposition audible. The chant "We can't drink data!" circulated through the audience. It was blunt, and it landed on a real local concern.
East Fishkill's groundwater supply is already under strain. Three Superfund sites affect the town's groundwater. For many residents, the idea of adding a 1,000-megawatt data center campus to that context, drawing heavily on local water resources for cooling, was not an abstract policy question.
Rosemary DaCruz, speaking for the community group For The Many, raised concerns about the town's capacity to absorb a project of this magnitude without independent environmental assessment. Resident Chris Frolick also addressed the board. The hearing record reflects a community that did not wait for a formal permit application before engaging. The NYISO queue entry and word of the concept had been enough.
What D'Alessandro Said in May
Before the moratorium vote, before the lawsuit, D'Alessandro had already encountered the project in conversation. In May, he described a brief exchange with Treetop to lohud. His recollection was pointed: "They don't have the power. Definitely not 1,000 megawatts."
That comment captured a core constraint facing any developer proposing a large load in Dutchess County right now. The mid-Hudson Valley's electrical grid does not currently have the spare capacity to absorb a 1,000-megawatt demand. The supervisor's assessment was grounded in physical reality, not politics. No formal proposal had been made to the town at the time of that conversation.
The Legal Argument
Treetop's amended complaint targets the moratorium's duration and its apparent purpose. The company argues that "a three-year development freeze is grossly disproportionate to any legitimate municipal planning need, constitutes an abuse of the Town's zoning authority, and amounts to an unconstitutional, temporary regulatory taking."
The attorney framing puts the online discourse and the June hearing crowd at the center of the legal theory. The company argues the town acted because of public pressure about its project specifically, before any application was reviewed on its merits. The company letter entered into the lawsuit record shows substantial coordination with NYISO, Central Hudson, Con Edison, and the New York Power Authority. Treetop cites that coordination to demonstrate the concept was not speculative.
The constitutional question is whether a three-year moratorium, applied broadly to all large data centers but allegedly motivated by one company's unfiled project, constitutes a taking that requires compensation. That question is now before a state Supreme Court judge in Poughkeepsie.
97 Towns and Counting
East Fishkill is not acting alone. A USA TODAY Network review of local actions over the past year found that 97 municipalities across New York have adopted temporary blocks on data center development. Eight towns have gone further and enacted outright bans. At least seven municipalities adopted new moratoriums in October alone.
The duration of these local freezes varies. Some run 12 months. Others cap at six months. Several, including East Fishkill's, extend two to three years. The wave reflects a consistent pattern: communities that lack state-level guidance are creating their own, using the moratorium as a standard planning tool.
Hochul's Executive Order and the Pending Bill
Governor Hochul moved to standardize the state's approach in July. Executive Order No. 62, signed on July 14, 2026, paused Department of Environmental Conservation permitting for data centers drawing 50 megawatts or more. The pause is expected to last roughly one year. During that period, the Department of Public Service will develop a Generic Environmental Impact Statement to assess the cumulative effects of large data centers on the grid, water supply, and surrounding communities.
Hochul stated: "The moratorium I signed is ensuring we develop a framework that meets the needs of New Yorkers - full stop. We are the first to enact this bold vision and we will be the first to get this right."
State lawmakers passed a separate bill with a broader 20-megawatt threshold in June. That bill is still pending. Advocates are pressing for a signature before a December deadline. Beth Finkel, New York State director of AARP, welcomed the executive order. AARP's concern centers on consumer protection and affordability: large data centers place significant demand on the grid, and that demand can translate into higher utility rates for residential customers.
The Industry's Counter
Not all observers view the freeze wave as sound policy. The Data Center Coalition, responding to USA TODAY Network reporting, argued that the economic opportunity at stake is substantial. Dan Diorio, the coalition's executive vice president of state policy, pointed to the jobs and supply chain activity that large data center projects generate. Electricians, steamfitters, pipefitters, and operating engineers are among the trades that see direct employment from these builds.
Diorio's argument is that freezing development does not reduce demand for data processing. It shifts it. Projects blocked in New York will find permitting in other states. The jobs and tax revenue leave with them.
A Case Heading to the Courts
The lawsuit in Poughkeepsie now frames the central legal dispute. Treetop Development says the moratorium was adopted in direct response to its concept, before any application was filed, and that a three-year freeze cannot be justified as ordinary planning. East Fishkill says it acted within its authority to pause, study, and protect existing residents from industrial impacts it does not yet understand.
The state is separately drawing its own lines, using executive authority and pending legislation to define the terms under which any hyperscale data center can operate in New York. East Fishkill sits inside all of those pressures at once. The moratorium runs through July 1, 2029. The lawsuit is now before a judge.
Sources
- 97 NY towns halted data centers on top of Hochul's state moratorium - lohud, Nov 25, 2026
- East Fishkill sued over data center freeze - Poughkeepsie Journal, Nov 25, 2026
- This new Dutchess County data center project would use as much power as a city - lohud, May 7, 2026
- East Fishkill passes 3-year data center freeze - WAMC, June 26, 2026
- Governor Hochul highlights first statewide moratorium on new hyperscale data centers - Governor of New York